Decommissioning of the current 54 wind turbines, with a diameter of 47 m, with a total installed capacity of 36.6 MW.
Les Colladetes Wind Farm
El Perelló, Baix Ebre

Wind farm repowering project funded by the Next Generation EU program, managed through the Spanish Government’s Institute for the Diversification and Saving of Energy (IDAE): from 54 to 6 wind turbines, while maintaining the same installed capacity.
Installation of 6 new wind turbines with a diameter of 158 m, maintaining the same installed capacity of 36.6 MW.

The repowering of Les Colladetes Wind Farm delivers:
- Reduced environmental and visual impact by replacing 54 turbines with only 6, while maintaining the same installed capacity.
- Enhanced energy quality, as the new wind turbines integrate cutting-edge technology to improve grid reliability and stability.
- Increased energy efficiency, leading to higher expected electricity generation. The superior performance of the new turbines will prevent the emission of 16,196 t of CO₂ into the atmosphere compared to the original project.